Lyari Transformation Project

Rs 25.28 Billion | 13 Union Councils | 4-Year Timeline (2026-2029)

Rs 25.28B
Total Budget
13
Union Councils
4
Year Timeline
2029
Target Completion
Overall Project Progress 8% Complete

Phase 1 initiated April 2026. PC-1 approved. Initial infrastructure work pending across all UCs.

Project Timeline

PC-1 Approval

Project Concept-1 approved by Sindh government

March 2026

Formal Inauguration

LG Minister Syed Nasir Hussain Shah inaugurates project in Lyari

April 9, 2026

Phase 1: Basic Infrastructure

Road construction/rehabilitation, new water supply lines, sewerage upgrades, stormwater drain cleaning

April 2026 - December 2026 (Expected)

Phase 2: Underground Cabling

Electricity infrastructure improvement, underground cable installation

2027 (Expected)

Phase 3: Beautification

Parks, green belts, public spaces, urban aesthetics

2028 (Expected)

Completion & Handover

Final inspection, documentation, public audit

2029 (Target)

Budget Allocation

Component Description Amount
Roads & Streets Construction, rehabilitation, pothole repair across 13 UCs Rs 8.5B (est.)
Water Supply New pipelines, pumping stations, solarization Rs 5.2B (est.)
Sewerage & Drainage Sewer lines, stormwater drains, treatment Rs 4.8B (est.)
Underground Cabling Electricity infrastructure, cable installation Rs 3.5B (est.)
Beautification Parks, green belts, public spaces Rs 2.0B (est.)
Solarization Pumping stations, street lights Rs 1.28B (est.)
TOTAL Rs 25.28 Billion

Union Council Progress

UC-1 Agra Taj Colony Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-2 Daryaabad Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-3 Nawabad Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-4 Khada Memon Society Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-5 Baghdadi Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-6 Moosa Lane Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-7 Shah Baig Line Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-8 Bihar Colony Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-9 Ragiwara Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-10 Singo Line Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-11 Chakiwara Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-12 Allama Iqbal Colony Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started
UC-13 Jinnahabad-Ghulam Shah Lane Pending
0% Complete
  • Road repair Not started
  • Water supply Not started
  • Sewerage Not started
  • Street lights Not started

Before / After Mockups

Visual targets for what each component will look like upon completion. Photos will be added as work progresses.

🛤

Roads & Streets

Smooth asphalt, proper drainage, pedestrian walkways

[ Before Photo ]
[ After Photo ]
💧

Water Supply

24/7 piped water, solar-powered pumping stations

[ Before Photo ]
[ After Photo ]
🚽

Sewerage System

Covered drains, treatment plants, no open sewage

[ Before Photo ]
[ After Photo ]
⚡

Underground Cabling

No overhead wires, reliable power, safe streets

[ Before Photo ]
[ After Photo ]
🌳

Parks & Green Belts

Public spaces, trees, playgrounds for children

[ Before Photo ]
[ After Photo ]
💡

Street Lighting

Solar-powered LED lights, safe nighttime movement

[ Before Photo ]
[ After Photo ]

Key Officials & Accountability

Role Name Party Responsibility
LG Minister, Sindh Syed Nasir Hussain Shah PPP Approved PC-1, inaugurated project, owns 2029 delivery timeline
Municipal Commissioner Hamad Khan Loran Civil Service Oversees solarization of pumping stations, cross-UC execution
TMC Lyari Chairman Khalil Hoath PPP Ward-level execution, public accounting of funds received
Sindh Chief Minister Murad Ali Shah PPP Provincial oversight, budget allocation